If you’d like to apply multiple changes in availability and allocation of resources? This can be done in the Resource management tab in the concerning resource pool.
- From your home page, go to the desired OU and choose the resource pool.
- Then click on the Resource Management tab and select the desired tab (Request & Allocation (Projects), Request & Allocation (Resources)or Availability (Resources)).
- Then click on Meerdere wijzigencode> at the top right.
- A pop-up screen will be shown, which can be used the makes the desired changes.
- First select all resources for which you want to make changes.
- Then select the type of the change:
- Set availability
- Set allocation
- Removal of availability / allocation from all projects / NPAs
- Then select the periodfor which you want to make changes (from – to date)
- If you want to set availability or allocation, you also need to enter the number of hours.
- When setting allocation, you also need to select an associated project.
- Then click on Wijzigcode> to make the changes.